The objective of the Chittagong Water Supply Improvement and Sanitation Project for Bangladesh is to increase the sustainable access to safe water and improved sanitation, as well as support the establishment of a long term water supply, sanitation and drainage infrastructure development and operational management program in Chittagong. The project has the following components: the first component being water supply and sanitation; the second component is the sewerage and drainage; and finally, the third component is the institutional and operational development, and project management support. The changes include: (i) scaling down project interventions in the water supply and sanitation component; (ii) cancelling some project activities under the sewerage and drainage component; and (iii) amending the project development objective, or PDO and results framework to correspond with the revised project scope.
Donor | Date | Amount (USD) | |
---|---|---|---|
1. | World Bank | 30 Jun 2010 | 170,000,000 |
2. | World Bank | 31 Mar 2014 | -14,478,062 |
3. | World Bank | 30 Jun 2017 | 47,490,000 |
4. | World Bank | 30 Sep 2019 | -9,999,995 |
5. | World Bank | 31 Dec 2020 | -10,000,011 |
Total Commitment: 183,011,932 |
Donor | Date | Amount (USD) | |
---|---|---|---|
1. | World Bank | 30 Sep 2011 | 509,253 |
2. | World Bank | 30 Sep 2013 | 1,108,433 |
3. | World Bank | 31 Dec 2013 | 2,545,839 |
4. | World Bank | 31 Mar 2014 | 2,820,785 |
5. | World Bank | 31 Dec 2014 | 583,559 |
6. | World Bank | 31 Dec 2014 | 11,858,018 |
7. | World Bank | 31 Mar 2015 | 3,611,367 |
8. | World Bank | 30 Jun 2015 | 8,042 |
9. | World Bank | 30 Sep 2015 | 7,661,124 |
10. | World Bank | 30 Sep 2015 | 14,613,901 |
11. | World Bank | 31 Mar 2016 | 12,071,231 |
12. | World Bank | 30 Jun 2016 | 1,863,199 |
13. | World Bank | 30 Sep 2016 | 7,053,506 |
14. | World Bank | 31 Dec 2016 | 10,882,158 |
15. | World Bank | 31 Mar 2017 | 10,100,557 |
16. | World Bank | 30 Jun 2017 | 4,711,191 |
17. | World Bank | 30 Sep 2017 | 4,956,629 |
18. | World Bank | 31 Dec 2017 | 4,947,434 |
19. | World Bank | 31 Mar 2018 | 4,225,522 |
20. | World Bank | 30 Sep 2018 | 1,791,045 |
21. | World Bank | 30 Sep 2018 | 2,441,267 |
22. | World Bank | 31 Dec 2018 | 2,625,298 |
23. | World Bank | 31 Mar 2019 | 2,382,370 |
24. | World Bank | 31 Mar 2019 | 2,739,726 |
25. | World Bank | 31 Mar 2019 | 1,186,944 |
26. | World Bank | 31 Mar 2019 | 3,560,831 |
27. | World Bank | 30 Jun 2019 | 4,142,012 |
28. | World Bank | 31 Aug 2019 | 2,366,864 |
29. | World Bank | 31 Aug 2019 | 3,550,296 |
30. | World Bank | 30 Sep 2019 | 2,366,864 |
31. | World Bank | 30 Sep 2019 | 3,550,296 |
32. | World Bank | 31 Jan 2020 | 5,889,282 |
33. | World Bank | 29 Feb 2020 | 5,889,282 |
34. | World Bank | 29 Feb 2020 | 3,531,489 |
35. | World Bank | 31 Mar 2020 | 5,889,282 |
36. | World Bank | 31 Mar 2020 | 3,531,489 |
37. | World Bank | 30 Jun 2020 | 2,944,641 |
38. | World Bank | 30 Jun 2020 | 3,062,426 |
39. | World Bank | 31 Aug 2020 | 2,173,349 |
40. | World Bank | 31 Aug 2020 | 2,358,491 |
41. | World Bank | 30 Sep 2020 | 2,173,349 |
42. | World Bank | 30 Sep 2020 | 2,358,491 |
43. | World Bank | 31 Dec 2020 | 2,358,491 |
Total Disbursement: 180,995,623 |
Name | |
---|---|
1. | Government |
Sector | Sub-sector | ||
---|---|---|---|
1. | Water Resources | 100.00% |
Location | ||
---|---|---|
1. | Chattogram, Chattogram | 100.00% |
Total: | 100% |
Indicator Title | Indicator Type | Baseline Year | Baseline Value | |
---|---|---|---|---|
1. | Total Value of Priority Sanitation and Drainage Investments Identified, Prepared, and Ready for Financing | Output | 2010 | 0.00 |
2. | Number of people in urban areas provided with access to Improved Water Sources under the project | Output | 2010 | 1500.00 |
3. | New piped household connections that are resulting from project intervention | Output | 2010 | 650.00 |
4. | Water Utility Maturity Level | Output | 2010 | 2.00 |
5. | Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Output | 2010 | 0.00 |
6. | Improved community water points constructed or rehabilitated under the project | Output | 2010 | 0.00 |
7. | Number of water utilities that the project is supporting | Output | 2010 | 1.00 |
8. | Number of other water service providers that the project is supporting | Output | 2010 | 0.00 |
9. | Volume of safe water produced by CWASA (Million liters per day - MLD) | Output | 2010 | 179.00 |
10. | Volume of safe water sold/billed by CWASA (Million liters per year # MLY) | Output | 2010 | 54816.00 |
11. | Number of staff trained as per approved staff training and development program | Output | 2010 | 0.00 |
12. | Number of zonal offices refurbished and equipped under the project | Output | 2010 | 0.00 |
13. | CWASA achieve O&M cost coverage from direct water sales revenues | Outcome | 2010 | 66.00 |
14. | CWASA's bill collection ratio | Output | 2010 | 97.00 |
15. | Percent of instituional capacity development activities supported by the project that are completed | Output | 2010 | 40.00 |
16. | Sanitation and drainage strategy and master plan prepared and approved by CWASA board | Output | 2010 | No |
17. | Institutional capacity development program prepared and approved by CWASA approved | Output | 2010 | No |
18. | New organogram prepared and approved by CWASA board | Output | 2010 | No |
19. | Staff training and development program prepared and approved by CWASA Board | Output | 2010 | No |
20. | Standard operating procedures and O&M manuals prepared and staff trained in their use | Output | 2010 | No |
21. | Commercial management plan prepared and approved by CWASA Board | Output | 2010 | No |
22. | Management information systems plan prepared and approved by CWASA Board | Output | 2010 | No |
23. | Customer services improvement plan prepared and approved by CWASA Board | Output | 2010 | No |
24. | Length of new pipelines installed | Output | 2010 | 7.50 |
25. | Length of pipeline replace / rehabilitated | Output | 2010 | 0.00 |
26. | Total value of priority sanitation and drainage investments identified, prepared and ready for financing | Outcome | 2010 | 0.00 |
27. | Number of people in urban areas provided with access to Improved Water Sources under the Project | Outcome | 2010 | 1500.00 |
28. | Water utility maturity level | Outcome | 2010 | 0.00 |
29. | Percentage of instituional capacity development activities supported by the project that are completed | Output | 2010 | 40.00 |
30. | Water Utility Maturity level | Outcome | 2010 | 0.00 |
31. | Sanitation and drainage strategy and master plan prepared and approved by CWASA Board | Output | 2010 | No |
32. | CWASA's Bill Collection Ratio | Output | 2010 | 97.00 |
33. | Institutional capacity development program prepared and approved by CWASA Board | Output | 2010 | No |
34. | Management Information Systems plan prepared and approved by CWASA Board | Output | 2010 | No |